According to project chief Shyamji Bhandari, the construction of headworks including dam under package 1, main tunnel, powerhouse and related equipment under package 2 and 220 KV transmission line in Damauli Bharatpur under package 3 are going on.TAG_OPEN_div_27
Tanahun hydropower project makes 78 per cent physical progress
Under package 1, the construction of the dam and other structures is being done by Songda Kalika JV. Bhandari said that 63 percent physical progress has been made in this package. For the construction of the main dam, the construction of hill erosion, access road, temporary dam to divert the flow of Seti River, two diversion tunnels has been completed.TAG_OPEN_div_25