Coordinator Dangol directs to include environmental aspect while preparing infrastructure development plan
लगानी न्यूज
. Kathmandu Metropolitan City deputy mayor and monitoring committee coordinator Sunita Dangal directed the department to consider environmental and social aspects while designing the designs in the process of infrastructure planning, designing and cost estimation.
She made the directive while monitoring the project to lay stones from Jamal-Kamaladi-Asan, Bhotahiti-Asan, Asan-Balkumari-Machhindra Bahal to Indrachowk today.TAG_OPEN_div_28
}’If it is not possible to make the road itself refillable with water, then the water should be recharged by placing a water recharge pit. At the same time, the infrastructure, social expectations and needs already built in that place should be taken into consideration. The plan is sustainable and community-friendly. Dangol said.
‘How is the surface water drained on this road section? Will the water accumulate on the road and affect pedestrians, locals and business activities?”
The plan was to lay stones on this road section through the method of water replenishment. For this, a test was conducted on 100 meters of road for about a month. The plan was amended and implemented after the regular movement of vehicles made the construction of the road with water recharge unsustainable.
During the inspection, Suresh Kumar Rai, chief of the Public Works Department, informed that the monitoring was carried out.TAG_OPEN_div_20 The 900-metre-long road has a minimum width of 4.5 feet and a width of 12 feet. The stones are 12 inches long, 8 inches wide and 4 inches thick. IS Construction Services has bid Rs 3,51,14,000 through the public procurement process for the project, which is estimated to cost Rs 44.2 million.
The construction side was given a work order on July 9, 2081 to complete the work by the end of October 2082. According to Rai, the construction period has increased due to the test of water recharge in the ground and amendment of the plan.
According to Gangadhar Gautam, deputy director of the Project Evaluation and Monitoring Unit, minor errors were found during the monitoring.TAG_OPEN_div_16 Letters will be sent to the construction side to rectify these errors. Ward chairperson, executive members, ward members, disaster management and environment monitoring team along with locals participated in the inspection.