This station is the third largest among the power stations under the Nepal Electricity Authority (NEA) in terms of capacity and the second largest in terms of annual generation, generating 451.7 GW per hour in the last fiscal year.TAG_OPEN_div_22 The plant, which has already produced 293.5 gigawatt hours till mid-January of the current fiscal year 2082/83, was closed for its sustainable operation and maintenance work was started from February 15.
Marsyangdi hydropower project resumes power generation
Kapil Dev Manjan, chief of the center, said that during this shutdown, the work that was pending for many years and considered very challenging has been completed.TAG_OPEN_div_20 According to him, the protection of structures at risk due to erosion especially in the upper riparian area of the dam area and near the desander has been completed, and the damaged structure of the ‘Under Sluice Gate’, which is considered important to prevent sand from entering the tunnel, has been repaired and made operational.