Nabin Bista, information officer of the Dumre-Besisahar-Chame Road Project Office, said that the road has been damaged mainly in three places. Apart from this, dozens of small and big landslides have also damaged the road in different places. In some places, the road has collapsed and in some places, the river has cut the road.TAG_OPEN_div_19
30 meters of road submerged in Rambazar area, 10 days to resume Besisahar-Chame road
He said that bomb blasting is necessary to remove the big boulders. The Marsyangdi river has also eroded the road in Kotro area. Wooden bridges at two places have been washed away. The project is using two dozers to open the road and is preparing to bring one more dozer from Nuwakot. He said that preparations are underway to open the road by mobilizing all three dozers. We have also sought help from the hydropower project to open the road.TAG_OPEN_div_15