Kathmandu. The Nepal Electricity Authority has been granted permission to import 350 megawatts of electricity from India during the winter season this year.
The Central Electricity Authority, under India’s Ministry of Power, has permitted the Nepal Electricity Authority to import electricity for up to 17 hours daily at competitive rates from the Indian Energy Exchange Market Day-Ahead and Real-Time Market.
The authority will be allowed to import electricity from 1 Mangsir 2083 (17 November 2026) to 15 Saun 2084 (31 July 2027). Accordingly, daily electricity can be imported from IX at other times except between 5 AM and 8 AM and 5 PM to 9 PM.
According to the permit, a total of 350 megawatts of electricity can be imported through the Kataiya–Kushaha, Ramnagar–Surajpura, and Raxaul–Parwanipur 132 kV transmission lines, totaling 300 megawatts, and 50 megawatts through the New Nautania–Mainhiya 132 kV transmission line.
The authority’s Executive Director, Dirghayukumar Shrestha, said that since 350 megawatts of electricity import permission has been granted from India, managing electricity demand and supply during the upcoming winter season will be easier.
Due to the snowfall on the Trishuli River via Bhotekoshi in Rasuwa, damage to the hydroelectric project and transmission line caused the disconnection of projects with a capacity of 431 megawatts from the national electricity system.
Executive Director Shrestha stated that necessary preparations have been made to manage electricity demand and supply for the upcoming winter season, keeping this situation in mind.
Based on last year’s analysis of electricity demand and production conditions, it is estimated that this year, for the four months of Poush, Magh, Phagun, and Chaitra, electricity demand will exceed domestic production.
During this period, electricity imports from India have been observed. Especially during Magh and Phagun, it is estimated that a daily average of 450 to 500 megawatts of electricity will be continuously imported.
It is estimated that during peak hours with such high demand, 800 to 900 megawatts of electricity must be imported daily. In Poush and Chaitra, it is estimated that comparatively less electricity will be imported.
From the upcoming Baisakh onwards, the flow of water in rivers will gradually increase, leading to an increase in internal electricity generation, replacing imports, and the start of electricity exports.
56 MW export permission
The authority has also been permitted to sell a total of 56 megawatts of electricity generated from three hydroelectric projects in the Indian energy exchange market. The authority will be allowed to export this electricity from 1 Mangsir 2083 (17 November 2026) to 15 Saun 2084 (31 July 2027).