Magdi’s hydropower projects hit by disaster, from extended testing period to shutdown

nabil
global ime

Myagdi. The monsoon-related disaster has affected the power generation, transmission, and construction operations of the hydroelectric projects in Myagdi.

The floods and landslides in the Kali Gandaki and Myagdi rivers and their tributaries have damaged the dams, power plants, tunnels, transmission lines, and access routes of both operational and under-construction projects.

Due to the disaster, some projects have been completely shut down, while testing production and construction work in others have been affected. Work has slowed down due to disruptions in the transportation of construction materials and equipment to under-construction projects. This has prolonged the completion period and increased the risk of increased construction costs.

Erosion of the Kali Gandaki River has washed away two towers in Doba of Annapurna Rural Municipality-1 on the Dana–Khurkot transmission line under the 220 kV capacity Kali Gandaki Corridor, and one tower in Ratopani. The tower in Dhirchyang has suffered partial damage, while another tower in the Tiplang area is at risk.

After the transmission line was blocked, there were problems connecting electricity generated from the Northern Myagdi hydroelectric projects to the national system. According to Roshan Khadka, head of the Nepal Electricity Authority’s grid office in Pokhara, a temporary tower was built in Bhirakate, about two kilometers of wires were stretched, and electricity supply resumed from Ashoj 31 last year. The permanent reconstruction process of the damaged tower and transmission line has been advanced.

Electricity from Ghalemdikhola, Mristrikola, Nilgiri-1, Nilgiri-2, and Relekhola in Annapurna Rural Municipality-4, Narchyang, as well as the Thapakhola Hydroelectric Project in Mustang, has been connected to the national system through this transmission line.

Two hydroelectric projects in Annapurna Rural Municipality have been shut down due to floods and landslides. The six-megawatt capacity Relekhola project was shut down after flooding from the Relekhork area deposited gash in the dam, said project representative Homnath Pandey. Similarly, the power house of the 14-megawatt Gharkhola project was buried by a dry landslide on the 26th of Saun.

Since then, the floods and landslides of last August have caused further damage to the dam. One person died and one person was injured when the power plant collapsed. Reconstruction preparations are underway, and according to preliminary estimates, the damage has exceeded one billion, said Anil Tiwari, head of administration at Magdi Hydropower.

The construction of the 180-megawatt capacity Kali Gandaki Gorge and the 66.3 megawatt Madhyakali Gandaki project under construction in the Kali Gandaki Basin have been affected for one and a half months. Senior manager Krishnadas Shrestha said work was halted after flooding caused a flood at the dam construction site at Thapla in Mustang, Kaligandaki Gorge.

The flood damaged the dam, tunnels, housing, machinery, equipment, construction materials, and diesel tankers in Sukebgar of the Madhyamakali Gandaki Project, said Chandra Prasad Dhakal, chairman of the promoter Hydro Support Pvt. Ltd., chairman of the IME Group. The flood has damaged the diversion of the construction site, as well as residential buildings in Nagdhunga and Ratopani, as well as the access road in Naulibagar area.

{{TAG_OPEN_div_32}The testing period of the 40-megawatt Rahughat Hydropower Project has been extended due to damage caused by erosion by the Kali Gandaki River in the power house area of Raghuganga Rural Municipality-3, Tilkenichaur. The area near the tailress gate and switchyard was damaged, and water entered the power plant causing flooding. Currently, two units of 20-20 megawatt capacity are being operated alternately for test production, said the managing director of the project, Ganesh KC.

The project under construction in the Myagdikhala Basin has also faced issues with access roads and transportation. Jyotikumar KC, the project chief of Upper Myagdikhola-1, said that landslides in the fields of Bhimaune, Balote, Banggelandha, Ilpu, and Shivaratri rivers have affected the transportation of construction materials and equipment. The construction of the Upper Myagdi project, which has made a total of 60 percent physical progress, has been affected. Landslides at various points along the roads of the Darkhola project have caused difficulties in transporting construction materials.

However, production from the Upper Rahughat, Mangale–Chimkhola–Rahughat, Upper Thulokhola, and Thaulokhola hydroelectric projects in the Rahughat Corridor is regular. Floods and landslides have exposed not only the main structures of the hydroelectric project but also transmission lines, access roads, construction material storage sites, and residential structures at risk.

To safeguard increasing investment in the hydropower sector, there is a need to make river erosion control, secure embankments, alternative access routes, transmission tower protection, and disaster preparedness integral parts of planning, construction, and operations.