The disaster has caused billions in damage to Magdi’s hydroelectric projects: production and construction affected

आयोजनाका बाँध, विद्युत्गृह, सुरुङ, प्रसारण लाइन र पहुँचमार्गमा असर

nabil
global ime

Magdi. This year’s monsoon-related disaster has severely impacted the production, transmission, and construction processes of Myagdi’s hydroelectric projects.

{{TAG_OPEN_div_105}Floods and landslides in the Kali Gandaki and Myagdi rivers as well as their tributaries have damaged dams, power plants, tunnels, transmission lines, and access routes for completed and under-construction projects.

Due to floods and landslides, some projects have been completely shut down, while electricity generation and testing in others have been affected. The pace of work has slowed down due to disruptions in the transportation of construction materials and equipment deployment in under-construction projects. This has also created risks of extending the completion period and increasing construction costs. Dozens of projects are under construction and operation in the Kaligandaki and Magdikhola basins, but the recent impact of natural disasters on the hydropower sector’s production structure and construction processes has raised questions about how crucial the security of physical infrastructure and disaster management are for energy development.

Power supply from the temporary tower

{{TAG_OPEN_div_99}The erosion of the Kali Gandaki River damaged the Dana–Khurkot transmission line under the 220 kV Kaligandaki corridor. The flood that washed away two towers in Aul and one in Ratopani in Annapurna Rural Municipality–1, Doba, caused partial damage to the tower in Dhirchyang. Another tower in the Tiplang area is also at risk of river erosion.

When the transmission line was blocked, there were problems connecting electricity generated from the hydroelectric project in the northern region of Myagdi to the national system.

According to Roshan Khadka, head of the Nepal Electricity Authority’s grid office in Pokhara, a temporary tower was constructed in the Bhirkate area, about two kilometers of wires were stretched, and electricity supply was restored from Asoj 31.

The authority has also announced that the reconstruction process of the flood-damaged transmission line and tower has also been advanced. Through this transmission line, electricity generated from the Ghalemdikhola (5 megawatts), Mristrikola (42 megawatts), Nilgiri-1 (38 megawatts), Nilgiri-2 (71 megawatts), Relekhola (six megawatts), and Thapakhola (14 megawatts) in Mustang in Annapurna Rural Municipality-4 Narchyang has been connected to the national system.

Two projects closed, billions in damage

{{TAG_OPEN_div_89}Two hydroelectric projects operating in Annapurna Rural Municipality have been affected due to floods and landslides. The six-megawatt Relekhola Hydroelectric Project was shut down after flooding from the Relekhark area of Narchang deposited sewage in the dam, said project representative Homnath Pandey.

{{TAG_OPEN_div_87}Similarly, after the dry landslide on the 26th of Saun flooded the dam of the 14-megawatt Gharkhola Hydroelectric Project, which was affected, the flood and landslide in the second week of Ashwin caused further damage to the dam. One person died and one was injured when the power plant was buried in the landslide. All equipment of the power plant was buried in the landslide. Anil Tiwari, an employee of promoter Magdi Hydropower, said that preparations for the reconstruction of the project are underway. According to him, preliminary estimates indicate that the project suffered losses exceeding one billion rupees due to the disaster.

Project construction affected in Kali Gandaki Basin

The work on the 180-megawatt Kaligandaki Gorge and the 66.3 megawatt Mid Kali Gandaki Hydroelectric Power Project under construction in the Kaligandaki Basin has also been affected for a month. According to Krishnadas Shrestha, senior manager of the Kaligandaki Gorge Hydroelectric Project, construction was affected after floods and landslides at the dam construction site in Thapla, Mustang, caused the construction work to accumulate sediment. The project had recently begun digging two audit tunnels.

According to Chandra Prasad Dhakal, chairman of IME Group, an investor in Hydro Support Pvt. Ltd., the promoter of the Madhyakali Gandaki Hydroelectric Project, the Kaligandaki River flood has caused significant damage to the dam, tunnel, housing, machinery and equipment, construction materials, diesel tanks, and workshops. At the dam construction site located in Sukebgar, located on the border of Annapurna Rural Municipality-3 and 4, the flood that broke the diversion and entered has piled up sewage. Floods have also entered the tunnel’s audit. Residential buildings in Nagdhunga and Ratopani, Annapurna Rural Municipality-2, have collapsed and washed away the materials there.

The river has also washed away the access road to Pokhrebagar for the motorable bridge on the Beni–Jomsom–Korla road located in front of the under-construction underground power house in Naulibagar area. Dipendra Sharma, an employee of the civil contractor Rasuwa–Multi JV, said that the construction work was halted due to flood and landslide damage. According to him, due to the disaster, the construction period of the project is expected to be extended.

The trial period for Rahughat has been extended

After erosion by the Kali Gandaki River caused damage to the power house area located in Tilkenichaur, Raghuganga Rural Municipality-3, the testing period for the 40-megawatt Rahughat Hydropower Project has been extended. The flood damaged the tailress gate of the project, which is a subsidiary of Nepal Electricity Authority, Raghuganga Hydropower Promoter. After production from the power plant, the structure that sends water to the river was damaged, and the river changed its course, causing erosion near the switchyard. Water entered the power plant from the tail race, causing flooding.

{{TAG_OPEN_div_74}The project, which started test production in the first week of Asoj, was completely shut down due to flooding. Ganesh KC, managing director of Raghuganga Hydropower, said that damaged structures and equipment are being repaired and retested. According to him, currently two units of 20 megawatt capacities are being operated alternately for test production.

In addition to repairing the access road to the dam, the accumulated gaffer in the dam area on the border of Jhin-Dagnam has been removed. The flood has also eroded about 150 meters of the Beni–Jomsom–Korla road along with the power station area of the Rahughat project. The switchyard is at high risk, and vehicles and equipment belonging to the civil contractor Jayprakash Associates have also been washed away.

Transportation issues in the Magdikhola Basin

Hydroelectric projects under construction in the Myagdikhol Basin have also been affected by floods and landslides. Jyotikumar KC, project chief of Upper Myagdikhola-1, said that due to landslides in Phopakhet, Balote, Bangelandha, and Ilpu, as well as flooding in the Shivaratri stream, there are problems in transporting construction materials and equipment. According to him, vehicles carrying cement, rods, and other construction materials and equipment have not been able to reach the project site since the disaster. Although work has been continued by deploying existing materials and equipment, construction has not progressed at the expected pace.

Because the motorable bridge being constructed by the Infrastructure Development Office over Shivaratri Khola is not completed on time, it becomes difficult for vehicles to cross during the rainy season. According to Buddhiraj Adhikari, Public Relations Officer of the Myagdikhola Hydroelectric Project, the rising water level in the river and landslides on the access road have affected the construction work. He said that vehicles carrying goods have to be towed with the help of dozers and vehicles are forced to clear landslides to pass through them.

The construction of the Upper Magdi Hydroelectric Project, which has made about 60 percent physical progress, has also been affected. Ramesh Subedi, head of the project, which is in the process of increasing its capacity from 37 megawatts to 46.25 megawatts, said that transportation of construction materials is necessary by changing vehicles at various places. Resham Bhandari, chairman of Darkhola Hydropower, said that construction materials could not be transported due to landslides on the Thaapachaur, Gauthili, and Dachaur cliffs on the Beni–Darwang and Darwang–Darwang–Dharapani–Takam–Muna roads.

Infrastructure Security and Disaster Management Challenge

Floods and landslides have not caused damage to all hydroelectric projects in Myagdi. Except for Rahughat, production in the Rahughat corridor is regular for other projects. Tundi Power Company’s 84-megawatt Upper Rahughat and Mangale–Chimkhola–Rahughat projects, as well as the 22.5 megawatt Upper Thulokhola and 23-megawatt Thaukhola hydroelectric projects, regularly operate.

The recent disaster has exposed not only the main structures of the hydroelectric project such as dams, power plants, and tunnels, but also access routes, transmission lines, construction material storage sites, and residential structures at risk. Changes in river course, accumulation of sediments, and landslides can affect the project’s regular operation and construction work. Because hydropower project construction requires significant investment and a long time, it seems necessary to make damage mitigation from natural disasters an integral part of the construction plan.

Floods and landslides not only disrupt production but can also increase the cost and time of projects under construction, affecting overall energy development goals and increasing investment risks. Special attention needs to be given to river erosion control, secure embankments, alternative access routes in risky areas, protection of transmission line towers, and disaster preparedness. As the potential for hydroelectric power generation and investment in Magdi increase, protecting related infrastructure from natural disasters has become equally important.