Target to generate 30,000 megawatts of electricity within 10 years: Preparation to open PPA through energy mix concept

nabil
global ime
फाइल फोटो

Kathmandu. The government has advanced the process of preparing a new energy mix policy based on the goal of producing 30,000 megawatts of electricity within the next 10 years.

The Ministry of Energy, Water Resources, and Irrigation has begun creating a new framework to determine the share of various sources of production. Once the new framework is ready, it is expected that the path will open to resume the long-stalled Power Purchase Agreement (PPA) process.

The new model being prepared by the Ministry of Energy will determine the proportion of electricity generated from river flowing (ROR), semi-aquiferous (PROR), reservoir-based, pumped storage, solar, wind, and other alternative energy sources.

This will lay the groundwork for what kind of events the country needs in the coming decade.

Currently, Nepal’s total installed electricity generation capacity is approximately 4,200 megawatts. A large portion of production comes from river-flowing hydropower projects. Since such a generation system is higher in the rainy season and less so in winter, diversification of energy sources is seen as necessary to manage seasonal imbalances.

Previously, the energy mix was determined based on a production target of 15,000 megawatts. But now, after the government has set a target of 30,000 megawatts of production, a new framework is being prepared, concluding that the old ratio cannot address long-term energy needs.

The National Energy Crisis Mitigation Policy and the Decade for Electricity Development (2016–2026) issued in 2016 for the first time determined the proportion of electricity generation from various sources. The target was to allocate 40 to 50 percent to reservoir-based and pumped storage projects, and 15 to 20 percent to semi-reservoir-based projects.

Later, according to the 15,000-megawatt production target, the share of reservoir-based and pumped storage projects was maintained at 30 to 35 percent, river flow 25 to 30 percent, semi-reservoir 30 to 35 percent, and other alternative energy sources from 5 to 10 percent. About 10 percent share was also proposed for solar energy. In Asar 2079, after the Cabinet increased the share of river flow projects to 40 to 45 percent, the PPA process changed accordingly. Subsequently, the Nepal Electricity Authority’s board of directors approved power purchase agreements for river-flow projects up to 1,500 megawatts.

The PPA process was further affected after the ‘take and pay’ system was implemented for river-flow projects through the last financial year’s budget. After that, PPAs for semi-reservoir-based projects along with river flows were also stopped.

According to the authority, so far 404 river flow projects have 6,713.44 megawatts, 51 semi-reservoir-based projects have 4,186.81 megawatts, and one reservoir-based project has 140 megawatts of power purchase agreements. However, an additional 281 projects totaling 16,425.77 megawatts of capacity are still awaiting PPA.

The absence of PPAs has affected the financial management required for project development. Since banks and financial institutions seek assurance for electricity sales, PPAs are considered the main foundation of the project’s financial reliability. Therefore, the new energy mix is expected to open the path for PPAs and also support private sector investment, construction activities, and job expansion.

Another important aspect of the new energy mix is giving space to alternative energy sources. Previously, Nepal’s electricity generation plan was mainly focused on hydropower, while the share of solar energy has been expanding. Wind energy generation is negligible.

Due to heavy dependence on hydropower, production decreases in winter and requires imports from India to manage electricity demand. To reduce this dependence, preparations are underway to include solar, wind, and other alternative energy systems in the energy system. The Ministry of Energy is studying the potential and production capacity of these sources.

The new energy mix is expected to help maintain a balance in electricity supply during both the rainy season and winter. In particular, reservoir-based and pumped storage projects can contribute to energy storage and supply management based on demand. Similarly, the development of solar and wind energy can increase production sources and temporal diversity.

Once the framework for the new energy mix is finalized, the Nepal Electricity Authority will be able to proceed with the PPA process based on the nature and needs of the project. This is expected to open the way for the development of projects with thousands of megawatts of capacity awaiting investment.

To meet the target of 30,000 megawatts of production, the challenge is to simultaneously advance domestic consumption, transmission infrastructure, and inter-country electricity trade alongside capacity expansion. Since increasing production alone will not be enough, a strategy to ensure electricity availability according to seasonal demand and expand export markets will also be necessary.

As Nepal expands the possibility of exporting electricity from India to Bangladesh, a balanced energy mix could help increase exportable electricity production. It will also expand opportunities to earn foreign currency through electricity trade.