Pokhara. Work is underway with the goal of completing the Ruptal Conservation and Integrated Development Project in Kaski within the current fiscal year.
Since the total progress of the project has exceeded 65 percent, the Irrigation and Water Resources Management Project, the taluk body of the project, Kaski, has stated that work is underway according to the target. The project provided this information to the Minister of Energy, Water Resources, and Irrigation, Biraj Bhakta Shrestha, who was present for the project monitoring.
During the inspection, Minister Shrestha stated that the government will facilitate the timely completion of the project, which is considered extremely important for fairy tourism.
He also mentioned that if the project model succeeds, similar projects of the same nature can be carried out in other lakes as well. He instructed employees and construction professionals to work at a fast pace and mentioned that the ministry would provide necessary facilitation to complete the project. The project, estimated to cost 4.5166 billion rupees, has so far spent 2.96 billion rupees on this project. This is 65.48 percent of the total estimated cost. The detailed project report (DPR) for the project, established in fiscal year 2073÷74, was approved in 2074 Saun.
The main objective of the project, which includes wards No. 31 and 32 of Pokhara Metropolitan City and Rupa Rural Municipality, is primarily aimed at protecting Ruptal, managing watersheds, controlling floods and erosion, and promoting tourism.
Under the project, the construction of a 635-meter-long dam, spillway and bridge, soil management of the lake, roads, footpaths, ecotourism gardens, and artificial islands and temples in the middle of the lake are proposed. Currently, work on the dam and spillway is progressing in the project. So far, 164.7 million rupees have been spent on the contract contract contract worth 287.9 million rupees. The project states that the construction of the spillway-cum-bridge is in its final stage, and work on the main dam and office building is also underway.
Similarly, 7.9 kilometers of road paving work on the left bank of the lake has been completed. Soil management and dredging work is also underway in the lake. The physical progress of this work, costing 396.7 million rupees, has reached 75 percent. So far, more than 502,440 cubic meters of soil have been managed.
Under the project, all three silt traps, 12 watershed conservation ponds, and 106 bed bars and check dams have been completed. Out of the two concrete bridges, one has been completed, and according to the eight-kilometer river control target, six kilometers of embankment have been constructed.
The work of acquiring the necessary land for the construction of the project structure has also been advanced. According to the approved DPR, a total of 1,472 ropani of land needs to be acquired, but the current project requirement is 1,200 ropani. So far, 1,018 ropanis of land totaling 1,034 units have been acquired. During this process, 23 houses have been managed, and approximately 1.3 billion rupees have been spent on compensation and land acquisition. Out of a total of 569 trees to be cut in the project, 222 have been cut so far. The project has publicly reported that approximately 12.9 billion rupees have been spent for this purpose.
However, in the construction of the eco-foottrail, issues related to forestry and tree felling have posed challenges. Meanwhile, the Irrigation and Water Resources Management Project has allocated a budget of 689,449,000 rupees for various programs in the current financial year 2083/84, according to project chief Krishna Prasad Dumrakoti. Water resource conservation, tar market conservation, river control, landslide management, integrated river basin irrigation, water resource management, and irrigation institutional development are the main programs this year.
The project’s scope spans six districts: Kaski, Syangja, Tanahun, Lamjung, Gorkha, and Manang. In the coming days, preparations are also underway to advance projects to control Tanahun’s Chundi River and to protect Manang’s lake markets and Chame Bazaar.