Chitwan. With the progress of landslide prevention work in the Tuinkhola area of the Narayangadh–Mugling road, vehicle traffic will be suspended for five hours daily.
The District Administration Office in Chitwan has decided to close the road every day from 11 AM to 4 PM from Mangsir 13 until further notice.
Considering the potential risks during landslide prevention work, it was decided to stop all types of vehicle movement on the Narayangadh–Mugling road section at that time, said Assistant Chief District Officer Ishwari Prasad Sharma.
After the landslides in Tuinkhola did not stop, the Road Division Office in Bharatpur has started working to find a long-term solution by adopting special technology. Since last year, after problems of landslides and road blockages appearing not only during the rainy season but also in winter, various technologies have been adopted to prevent landslides.
A ‘nailling’ technique will be adopted to manage the slope of the cliff by removing large rocks, and strengthening the landslide-affected area by driving peg rods. Additionally, the Road Division office has stated that ‘horizontal drains’ and bioengineering (biotechnology) will be used to drain water from the cliffs.
TAG_OPEN_div_30 According to the nature of the slope, bioengineering methods will be adopted in two-dimensional and three-dimensional patterns, and the main use of nailing technology for landslide prevention is stated by Chief Engineer Amit Kumar Sharma of the Road Division in Bharatpur.
The work to prevent the Tuinkhola landslide, which had been halted since last August, is about to resume. He said that despite the road being blocked at Krishnabhir on the Prithvi Highway, work was carried out at Tuinkhola, and after the road became operational at Krishnabhir, work to clear the road at Tuinkhola was also halted.
TAG_OPEN_div_26 According to Sharma, judging by the condition of the road, it is necessary to close and operate for at least 15 days.