The hydropower project brought into operation by Daramkhola Hydro Energy Limited was connected to the central transmission line on October 15.TAG_OPEN_div_23 Although it was said that the hydropower would be constructed by 2065 BS, the hydropower project started construction only in 2077 BS has a generating capacity of 9.6 MW.
Daramkhola Hydropower Project starts commercial production
Initially, Gorkha Hydropower Company was supposed to construct the project, but now Daramkhola Hydro Energy Pvt Ltd has taken the responsibility of constructing the project.TAG_OPEN_div_21 Hydropower engineer Mithilesh Chaudhary said that a dam has been constructed at Kandebas of Galkot municipality-8 and a powerhouse has been constructed four and a half kilometers west to generate electricity. Chaudhary said that although 9.6 MW of electricity can be generated during the rainy season, only 6.6 MW is being generated in winter.