With the 132 kV Chobhar substation in operation, Kathmandu Valley’s electricity supply is expected to become more reliable

nabil
global ime

Kathmandu. The 132/11 kV Chobhar substation located in Kirtipur Municipality-6, considered crucial for further strengthening, reliable, and improving the Kathmandu Valley’s electricity supply system, has come into operation.

Two power transformers with a capacity of 45 MVA each have been installed at the Chobhar substation. Electricity is supplied to the substation from the Matatirth–Chobhar section, constructed under the Thankot–Chapagaon–Bhaktapur 132 kV double circuit transmission line project.

Nine 11 kV feeder lines have been arranged to distribute electricity from the substation to the local area. Of these, three feeders have been extended towards the Pulchok area of Lalitpur and six towards Kirtipur and surrounding areas. The feeders have been gradually charged and electricity supply has been started in the local area.

On Sunday, Nepal Electricity Authority’s Executive Director Dirghayu Kumar Shrestha inspected the substation and instructed the concerned officials to immediately charge the 11 kV feeders and move forward with the load transfer work.

Executive Director Shrestha said that once the Chobhar substation is operational, it will help manage the increasing electricity demand, especially in Kirtipur and surrounding areas and in the Pulchok area of Lalitpur. He mentioned that since the Kathmandu Valley’s electricity demand will rise during the winter season, the Matatirtha–Chobhar transmission line and Chobhar substation play an important role in supply management and directed that the load transfer work be completed immediately.

With the operation of the Chobhar substation, a portion of the electricity load supplied from the Syuchatar, Teku, Patan, and Matatirth substations will be transferred to the Chobhar substation. This is expected to help manage the load of existing substations and make the overall electricity supply system of the Kathmandu Valley more reliable.

Due to difficulties in acquiring the required land and other obstacles for the construction of the transmission line under the Thankot–Chapagaon–Bhaktapur 132 kV transmission line in Lalitpur’s Khokna, Bungmati, Harisiddhi, and Lamatar areas, the 132/11 kV substation was constructed as an alternative arrangement in Chovar.

The construction of a 132 kV underground transmission line, about four and a half kilometers long, from Chobhar substation to Patan has also been given high priority. Work is also underway to build a 132 kV substation in Patan. Once these structures are completed, the Kathmandu Valley’s electricity transmission and distribution system will be further strengthened.

The substation was constructed by renting 12 ropani and 12 annas of land owned by Himal Cement in Bhutkhel, Chobhar. The cabinet meeting on Magh 17, 2078, decided to lease this land to the Nepal Electricity Authority for substation construction. The Chobhar substation was constructed using a concessional loan received under the Asian Development Bank (ADB)’s Kathmandu Valley Transmission Capacity Strengthening Project.