According to the Suryabinayak-Dhulikhel, Dhulikhel-Sindhuli-Bardibas road project, 67 per cent physical progress has been made so far in the expansion of the 16-km road.TAG_OPEN_div_26
Suryabinayak-Dhulikhel road works 67 per cent in last three years
The deadline for the expansion of the eight-kilometer Sanga-Dhulikhel road was signed on December 11, 2079.TAG_OPEN_div_22 Lama Construction Pvt Ltd was awarded the contract for the construction of the project at a cost of Rs 4.05 billion. According to the road project, only 60 per cent of the road construction work has been completed during the period. According to Rabindra Shrestha, manager of the construction company, 65 percent of the total physical progress has been completed while 90 percent of the physical progress except pitch has been completed.