According to Nepal Army Colonel Chiranjivi Chaulagain, the construction of the bridge is being brought from Baireni and Bara of Dhading where the Nepal Army has stockpiled it. All the materials will reach Vetrawati by today. A team of 55 people of the Nepal Army will start installing the bailey bridge from Wednesday.TAG_OPEN_div_21
Bhotekoshi floods: Bailey bridge over Falakhu river linking Nuwakot and Rasuwa begins
Although it usually takes three days to install the bridge, the height of the old ‘jeep’ (bridge structure) has been increased by two meters. Colonel Chaulagain said that the target is to bring the bridge into operation till Phulpati of Dashain as it will take some time to dry the additional structure.TAG_OPEN_div_19