Ganesh KC, managing director of Raghuganga Hydropower, said that preparations are being made to test the physical infrastructures built with the aim of producing test by mid-May.TAG_OPEN_div_31 “Civil, hydro and electro-mechanical structures have been completed and finishing works are being done”, he said, adding, “We are preparing to test the tunnel by filling water after closing the four entry points to the tunnel”. ”
Rahughat hydropower project deadline extended for the fourth time, physical progress 95 per cent
Jai Prakash Associates (JP), an Indian civil contractor, had signed the contract for Rs 6 billion on November 17, 2017 with a target to complete the project in 45 months.TAG_OPEN_div_29 The deadline was extended for the first time in February 2022, the second time in February 2022 and the third time until November 2025. KC said works are being carried out as per the target of completing the project within the extended deadline for the fourth time.