According to the chief of the Nagdhunga-Sisnekhola Tunnel Way Project Saujanya Nepal, preparations have been made to bring the tunnel way into operation by the third week of July after making necessary preparations.TAG_OPEN_div_26 He said that technical works including training are being carried out by signing an agreement with the company collecting fees from the vehicles plying through the tunnel route.
Nagdhunga-Naubise tunnel road to come into operation from mid-July
As many as TAG_OPEN_div_22 150 employees have been recruited to operate the tunnel round the clock. These employees will be mobilized on a shift basis. Speaking at a meeting of the National Assembly’s Public Policy and Delegated Legislation Committee today, Project Chief Nepal shared that the project has achieved 99.5 per cent physical progress and 96 per cent financial progress.