Engineer Ishwar Nepal of the construction company responsible for the construction of the new track said that the construction work has reached the final stage. According to him, graveling, slope cutting and drainage construction work is going on on the 11th day today.TAG_OPEN_div_20
New track at Krishnabhir in final stage: Traffic to resume from September 1
He said, “We are probably going to start the work so that the traffic will be fully operational from September 17.” According to him, 11-12 equipment was deployed for 9 to 10 days in the first phase of construction. Now that the work is in the final stage, about 40-50 skilled and unskilled workers have been mobilized. Five to six heavy equipment, including graders, rollers and excavators, are being used as per the requirement.TAG_OPEN_div_18