Tanahun hydropower project to cost $505 million

nabil bank

Tannhu. The 140-megawatt Tanahun Hydropower Project has achieved 75 per cent progress so far.

According to the project, 75 per cent progress has been made in all three packages of the under-construction project at Rishing Rural Municipality-1, Jhaputar.TAG_OPEN_div_34

According to project chief Shyamji Bhandari, the construction of headworks including dam under package 1, main tunnel, powerhouse and related equipment under package 2 and 220 KV Damauli-Bharatpur transmission line under package 3 is going on.TAG_OPEN_div_32

Under package 1, the construction of the dam and other structures is being carried out by Songda Kalika JV.TAG_OPEN_div_30 Bhandari said that 57 percent progress has been made in this package. Construction of hill erosion, access road, temporary dam and two diversion tunnels have been completed for the construction of the main dam.

The Seti River was diverted on November 4, 2080 for the construction of the main dam.TAG_OPEN_div_28 The construction of temporary dams in the upper and lower banks of the main dam was completed in May 2081.

With the completion of this work, the necessary infrastructure has been prepared to start the ‘concreting’ and related grouting work of the main dam.TAG_OPEN_div_26 “The first concrete was laid on Chaitra 7, 2081 BS for the construction of the 140-meter tall dam,” he shared, adding that the concrete, core drilling and grouting of the main dam are going on. ”

Under package 2, Sino Hydro Corporation is carrying out the work of power house and related equipment.TAG_OPEN_div_24 Bhandari said that civil construction of most of the structures has been completed and digging for the construction of underground structures has been completed by this period. Bhandari said that 76 percent progress of the package has been completed with the construction work of powerhouse, cable tunnel, search tank, tailrace and other structures.

According to Bhandari, concrete lining of the main tunnel used to divert water from the reservoir to the powerhouse is underway.TAG_OPEN_div_22 A total of 1418.75 meters of concrete lining has been completed so far.

KEC International Limited, India, has completed the construction of 78 towers out of 94 towers along the Damauli-Bharatpur 220 KV 33 kilometer transmission line.TAG_OPEN_div_20 The progress of this package is 77 percent. The printing work has started in coordination with the Division Forest Office concerned to remove the trees from the national forest which lies in the route of the transmission line.

The total cost of the project (including interest for transmission line, rural electrification and construction period) has been agreed by ADB with $150 million, Japan International Cooperation Agency (JICA) with $184 million, European Investment Bank with $85 million and Nepal government/Nepal Electricity Authority with $86 million as financial arrangement.TAG_OPEN_div_18